Carver construction: What to expect the week of Nov. 15
Carver construction activities for week of Nov. 15:
- Complete demolition of Gym D.
- Continue storm sewer site work.
- Begin “pin” pile installation.
- Noise will be similar to periodic jackhammering.
- Continue drilling “micro” piles in central corridor.
- Equipment noise & diesel fumes.
- Noise will be similar or less in intensity as previous demolition noise.
- First phase of piling scheduled to be complete late December/early January.
- Noise, odors, dust, truck traffic, vibrations.
Following week activities:
- Roof abatement at south “eyebrow” of Gym C overhang tentatively scheduled for Nov. 23, 24 and 25. All required precautions & regulations to protect workers & campus community will be followed. Monitoring & quality control for safety will be done by a third party.
- Complete storm sewer site work.
- Complete “pin” pile installation.
- Excavate utilidor.
- Complete “micro” pile drilling in central corridor & east section.
- Noise, odors, dust, truck traffic, vibrations.
For more information, contact Dale Krause, construction coordinator at 360-650-4646 or dale.krause@wwu.edu.