Multicultural Center construction Update: May 29

Multicultural Center construction activities for the next several weeks:

Safety

  • To address safety concerns, the area around the construction site will be designated as a bicycle/skateboard dismount zone. Bicyclists, skateboarders and pedestrians must use the sidewalks. Appropriate signage will be installed in early June. Please continue to use caution in this area.

Demolition

  • Small demolition tasks continue. Last week contractors cut a hole in the 6th floor of the old bookstore for the new staircase that will access the 5th floor, see photo below.

New Construction

  • Over the next couple weeks new construction focuses on structural columns, pilasters and footing to support the new addition.  The biggest impacts will occur when contractors pour concrete using a pumping truck.  There may be odors and additional truck traffic on High Street.  

 

Contact info:

Forest Payne, Project Manager, 650-3218, forest.payne@wwu.edu

Dale Krause, On-Site Construction Coordinator, 650-4646, dale.krause@wwu.edu

Project web page: https://www.wwu.edu/wwuarchitect/construction/pw698.shtml

Project FAQ: https://www.wwu.edu/wwuarchitect/construction/pw698_faq.shtml