Carver construction: Updates for the weeks of Aug. 1 and Aug. 8
August 3, 2016
Carver construction updates for the weeks of Aug. 1 and Aug 8:
General Impacts:
- Pedestrian/vehicular detours remain in place.
- Contractor continues to mitigate noise, dust and other construction impacts as much as possible.
- Welding activities are shielded where possible
Areas of Focus:
Central Corridor:
- Roofing
- Rough-in mechanical/electrical/plumbing/fire systems
- Wall framing and door frames
- Wallboard installation
1959 Building/Gym A/B/C:
- Block wall installation Gym C
- Wallboard installation
- Shotcrete wall reinforcement
- Patch existing walls and slabs
- Rough-in fire system
- Roofing
Gym C South Addition/East Side Addition:
- Fireproofing
- Structural framing and decking
- Roofing
Gym D/1970 Addition:
- Rough-in mechanical/electrical/fire systems
- Wall framing and door frames
- Wallboard installation
- Roofing
- Clean exterior masonry
For questions/concerns, please contact Dale Krause, construction coordinator at (360) 650-4646 or dale.krause@wwu.edu.