Birnam Wood Moisture Mitigation Phase 2 construction update

Construction update on the Birnam Wood Moisture Mitigation Phase 2 project for the weeks of Aug. 1 and 8:

The waterproof membrane has been applied to the foundation walls and installation of new drainage lines and backfill has begun.

Construction Impacts:

  • Stacks 6 and 7 are closed
  • Parking lot is partially closed
  • Equipment noise and fumes expected

 

Current Projects:

Week of Aug. 1-8:

  • Insulate and cover in crawl space at Stack 7
  • Seal crawl space envelop at Stack 6
  • Install pipe drain lines at Stack 6 and Stack 7
  • Backfill at Stack 6 and Stack 7
  • Install French drains at Stack 6 and Stack 7
  • Finish grades at Stack 6 and Stack 7

Week of Aug. 8-14:

  • Seal crawl space envelop at Stack 7
  • Backfill at Stack 6 and Stack 7
  • Install French drains at Stack 6 and Stack 7
  • Finish grades at Stack 6 and Stack 7
  • install clean out covers
  • Install timber landings

 

Maintainence and Custodial Personnel:

Thank you again for your continued cooperation! When approaching the work area for cleaning, painting or other maintenance, use caution and be safe.! Wear a hard hat, communicate your presence with HB Hansen site superintendent, Jason Tyree, and ensure equipment operators acknowledge your location.

Should you have questions, please contact the Project Manager, Doug MacLean at (360) 650-3791 or doug.maclean@wwu.edu.